Mornington BESS: 33kV Switchgear and End-to-End Commissioning

240 MW Power
480 MWh Energy
Mornington Peninsula, Victoria Location
ACLE Services Pty Ltd Client
2025 Completion
Client
ACLE Services Pty Ltd
Principal Contractor
ACLE Services Pty Ltd
Developer
Maoneng / GMR joint venture with Gaw Capital Partners (original)
Asset Owner
Valent Energy
Location
Mornington Peninsula, Victoria, VIC
Grid Connection
AusNet Tyabb Terminal Station
Capacity
240 MW / 480 MWh
Voltage
33 kV
Battery OEM
Genesis TD
PCS-side Switchgear
Ormazabal with ABB REJ603 protection relays
Asset Type
Utility-scale BESS — 33kV ABB GIS, 2 switchboards
Project Type
BESS commissioning — FAT, SAT, protection, SCADA, PCS, battery discharge
Duration
Commissioning complete (project codes MVPROJ_12909 and MVPROJ_13448)
Megavar Scope
T&C lead for FAT, SAT, protection, SCADA and battery discharge
Technicians Performing High Voltage (HV) Substation Commissioning Inside a Control Room
Technician Inspecting Equipment During High Voltage (HV) Substation Commissioning

Overview

The Mornington BESS is a 240MW / 480MWh utility-scale battery energy storage system on Victoria’s Mornington Peninsula, connected to the national grid at AusNet’s Tyabb Terminal Station. Asset owner Valent Energy (originally a Maoneng / GMR joint venture with Gaw Capital Partners) engaged ACLE Services as EPC, and ACLE contracted Megavar to deliver the testing and commissioning programme across the high-voltage and battery systems.


Megavar’s scope covered factory and site acceptance testing of the 33kV ABB GIS switchgear, protection and SCADA testing, PCS primary and secondary commissioning, field transformer testing, battery discharge testing and end-to-end integration to the AusNet grid. At peak delivery the Megavar team fielded 7 to 8 testers and engineers on site.


A significant portion of the HV testing was witnessed by the Victorian Electrical Safety Inspector to confirm testing was performed safely and to the relevant standards. The project energised successfully and is now in commercial operation.

Scope of Work

Factory Acceptance Testing (FAT)

  • 33kV ABB GIS switchgear FAT at SRS Power, including withstand, circuit breaker timing and timing curve verification, CT ratio and polarity, earth switch operation and interlock proving
  • Relay FAT testing on the assembled switchboards

Site Acceptance Testing (SAT) and Primary Plant Commissioning

  • 33kV ABB GIS switchgear SAT following site installation
  • PCS RMU testing: withstand, circuit breaker, CT, earth switch, interlocks and ABB REJ603 relay function checks across each PCS enclosure
  • PCS transformer testing using Omicron CPC 100 and Testrano 600
  • Field transformer testing across the wider BESS LV distribution
    LV distribution and breaker testing

Protection and Secondary Systems

  • 33kV switchboard protection setting audit across both switchboards
  • PCS secondary protection testing and functional checks
  • PQM (power quality metering) device testing
  • Relay typicals and logic verification against the issued protection scheme

SCADA and Integration

  • DNP3 map verification and rebuild across the 33kV protection relays
  • Typicals testing to an external RTU prior to full SCADA testing
  • End-to-end SCADA and alarm point testing through to the
  • AusNet integration boundary

Battery System

Battery discharge testing through multiple phases, supporting commissioning and grid compliance

Test Equipment
Deployed on Site

  • Omicron CMC 356: Protection relay testing and secondary injection
  • Omicron CMC 500: Protection and system-level testing
  • Omicron CPC 100: Primary injection, transformer testing, earth testing
  • Omicron Testrano 600: Three-phase transformer testing
  • Omicron Cibano: Circuit breaker timing and dynamic analysis
  • Omicron CMLIB REF: Reference for GPS-synchronised CMC testing
  • Omicron CT Analyzer: CT ratio, polarity and saturation testing
  • Megger Torkel 930: Battery bank discharge testing
  • Megger MIT 515 (5kV): Insulation resistance testing
  • Megger MOM2: Circuit breaker contact resistance
  • Megger DLRO 100: Low resistance ohmmeter testing
  • BK130: High-current AC injection
  • Fluke 189: General multimeter and verification

Megavar deployed a full Omicron test suite supported by Megger and Fluke instrumentation. Each instrument listed here is available for hire separately.

New ABB UniGear ZS1 11 kV switchgear in service at Chapel Street Substation, commissioned by Megavar

Challenges and Approach

No DC supply on site for 33kV switchgear testing

When Megavar mobilised to the manufacturing site and then to the SAT site, no DC supply was available to power the two 33kV ABB GIS switchboards for testing. Under the Principal Tester’s direction, Megavar’s project manager sourced and purchased a DC power supply rated to power both switchboards, together with additional HV cable termination caps to prevent flashover and equipment damage during withstand testing. Testing resumed the same day, with no impact on the commissioning programme.

 

Incomplete ABB relay configuration and DNP3 mapping

The 33kV protection relays were delivered with typical configurations only. DNP3 point mapping was not complete from the OEM. During FAT, the incomplete relay settings were sent back to ABB to configure the DNP maps, which the end user then uploaded post-FAT. On upload, all relays went into alarm, creating an immediate integration issue with AusNet and the project SCADA.


Megavar mobilised back to site after hours, rebuilt the DNP mapping into the correct relay configuration files, and assisted ACLE to test the typicals into an external RTU before proceeding with full SCADA testing. This recovered the schedule and avoided a re-FAT of the relay panels.

 

PCS commissioning efficiency across a large site

The BESS layout required the test team to move between many PCS units across a large footprint. Rather than run extension leads and relocate test gear at every PCS, Megavar set up a mobile testing rig on the back of a UTE, powered by alternative power supplies (inverters). The UTE acted as an additional barricade alongside the standard delineation and reduced manual handling, trip hazards, noise exposure and mobilisation time between PCS units.


During PCS testing the team identified and flagged several faulty live line indicators, and one RMU with a circuit breaker that failed to open. These defects were raised with ACLE and rectified before the RMUs were placed into service.

Outcomes

Mornington BESS energised and entered commercial operation on programme despite the mid-project relay configuration and DC supply issues.


Every phase of HV testing that required inspector oversight was witnessed by the Victorian Electrical Safety Inspector.
Defects identified by Megavar during PCS testing (faulty live line indicators, failed RMU breaker) were corrected prior to energisation, avoiding post-energisation rework.


DNP3 mapping across both 33kV switchboards was rebuilt and verified against the external RTU, allowing clean handover to the AusNet interface.

Megavar engineer FAT testing a Siemens 7SJ82 feeder protection relay for Chapel Street 11 kV switchgear

Need High Voltage Testing or Equipment?

Talk to our engineers about your project requirements.

Get In Touch

Frequently Asked Questions

What does BESS commissioning involve?
BESS commissioning is the end-to-end process of proving a battery energy storage system is safe, compliant and ready to operate on the grid. It covers factory and site acceptance testing of the HV switchgear, protection and SCADA verification, PCS commissioning, transformer testing, battery charge and discharge testing, and integration testing to the transmission or distribution network. On a 240MW project, commissioning typically runs in parallel with construction for several months and culminates in a controlled first-time energisation sequence.
FAT (Factory Acceptance Testing) is the formal testing of switchgear at the manufacturer’s premises before it leaves the factory, confirming that the product meets specification. SAT (Site Acceptance Testing) repeats and extends that verification once the switchgear has been installed on site. On Mornington BESS, Megavar carried out both FAT (at SRS Power) and SAT on the 33kV ABB GIS switchboards, covering withstand, breaker timing, CT and earth switch operation, and protection relay function checks.
Megavar commissions BESS installations as a single T&C work package, covering HV switchgear, protection, SCADA, PCS, transformers and battery discharge testing under one team. Our engineers and testers work from FAT at the OEM factory through to SAT, energisation and grid integration, with a preference for Omicron instrumentation (CMC 356, CPC 100, Testrano 600, Cibano) and Megger battery test sets (Torkel 930). We have delivered BESS commissioning for ACLE Services across the Mornington Peninsula and Greater Shepparton in Victoria.
On Mornington BESS, Megavar deployed a full Omicron test suite including the CMC 356, CMC 500, CPC 100, Testrano 600, Cibano, CMLIB REF and CT Analyzer, supported by a Megger Torkel 930 for battery discharge, MIT 515 for insulation testing, MOM2 and DLRO 100 for breaker contact resistance, a BK130 for primary injection and a Fluke 189 for general verification. Every instrument listed is available for hire through Megavar’s equipment rental service.
DNP3 is the communications protocol used to exchange protection, control and alarm data between substation relays and the grid operator’s SCADA. If the DNP3 map in the relay does not match the SCADA master, the relay can flag every mismatched point as an alarm at startup, which can block integration with the transmission network. On Mornington BESS, Megavar rebuilt the DNP3 mapping across both 33kV switchboards after hours, which recovered the SCADA integration schedule with AusNet.
The Mornington BESS is on the Mornington Peninsula in Victoria, adjacent to AusNet’s Tyabb Terminal Station. The 240MW / 480MWh facility connects into the national grid at Tyabb and provides frequency, capacity and arbitrage services to the National Electricity Market.

Explore Our other services

Circuit breaker testing across Australia: timing analysis, contact and dynamic resistance, insulation and SF6/vacuum integrity testing on HV and MV breakers, fully reported.

Expert BESS commissioning services across Australia. Megavar delivers HV testing, protection validation, SCADA integration, and grid compliance for battery energy storage systems from 5MW to 500MW+.

Arc flash studies and hazard analysis across Australia: incident energy and arc flash boundary calculation to IEEE 1584, PPE and labelling, and mitigation design.

Trusted by top enterprises for exceptional results

AusNet logo - Megavar client
ABB logo - Megavar client
ElectraNet logo - Megavar client
Fluence logo - Megavar client
RJE Global logo - Megavar client
NYRStar logo - Megavar client
Schneider Electric logo - Megavar client
Acciona logo - Megavar client
RBD Electrical logo - Megavar client
Ventia logo - Megavar client
Grange logo - Megavar client
Alcoa logo - Megavar client
Zinfra logo - Megavar client
Bison Energy Company logo - Megavar client
Hydro Tasmania logo - Megavar client
TasNetworks logo - Megavar client
Vestas logo - Megavar client
Goldwind logo - Megavar client
Downer logo - Megavar client
ENERVEN logo - Megavar client
Genus logo - Megavar client

Explore the latest insights