St Marys Substation 110/22 kV Transformer Replacement
- Client
- TasNetworks
- Location
- St Marys Substation, east coast Tasmania, TAS
- Voltage
- 110 kV and 22 kV
- Asset Type
- 2 x 110/22 kV 10 MVA power transformers plus associated 22 kV protection, SCADA, station service transformer and ring main unit
- Project Type
- Asset replacement with end-to-end design, staged protection upgrade and full commissioning
- Duration
- Approximately 18 months end-to-end. Design scope November 2024 to IFC submission May 2025 (7 months). Testing and commissioning scope August 2025 to completion April 2026 (9 months).
- Megavar Scope
- Primary, secondary and SCADA design; staging and secondary isolation methodology; protection relay logic, settings and staged SEF check scheme; integration, testing and commissioning; closeout documentation
Overview
St Marys Substation sits on the east coast of Tasmania and supplies the distribution network that services Break O’Day and the surrounding east coast communities. The two 110/22 kV 10 MVA power transformers at St Marys, T1 and T2, had reached the point in their service lives where TasNetworks elected to replace them and upgrade the associated 22 kV protection at the same time.
TasNetworks engaged Megavar directly to deliver the project end to end. That scope covered the primary, secondary and SCADA design; the staging and secondary isolation methodology needed to remove the existing transformers safely; the protection setting work and a staged SEF check scheme to carry the site through each commissioning step; and the full testing and commissioning of the new equipment. The same Megavar team that produced the design package mobilised to site to commission it, which removes the design-to-commissioning interface risk that is normally carried between two contractors on a project of this size.
The work was executed on a live operational substation and sequenced around tightly controlled outage windows, with the 22 kV network supply to the east coast community needing to be maintained throughout. The project ran from design commencement in November 2024 through to commissioning completion in April 2026.
Scope of Work
- Primary (high voltage) design for the replacement of T1 and T2, including plant layout, clearances and interface with the existing 110 kV and 22 kV switchyards
- Secondary design covering protection, interlocking, DC supply, tripping, control and auxiliary schematics for the new transformers and associated 22 kV equipment
- SCADA design covering points lists, alarm and event integration, remote control, and indication for the new transformers, station service transformer and ring main unit
- Staging and secondary isolation methodology for the safe removal of the existing T1 and T2 while maintaining 22 kV supply to the east coast distribution network
- Interlocking scheme design for the 22 kV station service transformer, which is supplied alternately from 22 kV Bus A via feeder B252 or 22 kV Bus B via feeder H252 (one bus at a time)
- Staged Sensitive Earth Fault (SEF) check scheme design to accommodate the differing CT secondary ratings between the existing and new transformers during each phase of the staged commissioning
- Preliminary Design Package and Issued for Construction (IFC) Design Package production, submitted May 2025
Protection setting reports across the full relay suite, followed by protection setting files developed in the Megavar office from the approved setting reports - Inspection Test Plans and Commissioning Management Plans tailored to the staged outage sequence and TasNetworks acceptance requirements
- Site staging execution, secondary isolation, integration and commissioning of the two new transformers and the associated 22 kV feeder and protection equipment
- Protection relay commissioning across GE, Siemens, MicroTapp, Areva and RMS relay families
- Site Acceptance Testing (SAT) of a new 22 kV station kiosk
22 kV cable VLF (Very Low Frequency) withstand testing and partial discharge measurement - SCADA testing including point-to-point verification, alarm and event propagation to the network control room, and remote control proving
- Commissioning of a 500 kVA 22/0.4 kV station service transformer and a 22 kV ring main unit
- As-built drawings, commissioning records, and site handover package
Equipment
Commissioned
- 2 x 110/22 kV 10 MVA power transformers (T1 and T2)
- 2 x GE T60 transformer management relays
- 2 x Siemens 7UT613 transformer differential relays
- 2 x MicroTapp MT101 tap changer controllers
- 2 x Areva P143 protection relays (110 kV side)
- 5 x Areva P143 protection relays (22 kV side)
- 3 x Areva P122 protection relays (22 kV side)
- 1 x RMS 2C138 protection relay (22 kV side)
- 1 x 22 kV station kiosk (Site Acceptance Testing)
- 1 x 500 kVA 22/0.4 kV station service transformer
- 1 x 22 kV ring main unit
- 22 kV cable circuits (VLF and partial discharge proved)
- SCADA integration, communications and control room alarms
Megavar Test Equipment Deployed
- Omicron CMC 500 protection relay test set
- Omicron CMC 356 protection relay test set
- Omicron CPC 100 primary injection test set
- Omicron TESTRANO 600 transformer diagnostic test set
- Omicron MPD 600 partial discharge measurement system
- HV Diagnostics HVA60 VLF test set (22 kV cable testing)
- Phoenix 6CP50 50 kV HiPot test set
- Megger MIT 515 (5 kV insulation resistance tester)
- Megger DLRO 600 micro-ohmmeter
Team: Megavar delivered the project with a multi-discipline team across two phases. The design phase was led by a senior design engineer supported by primary and secondary design engineers and drafters. The testing and commissioning phase was led by dedicated T&C engineers supported by field testers. Overall project management sat with a dedicated Megavar project manager through the full duration.
Handing the project through from Megavar’s design team to Megavar’s T&C team meant the commissioning engineers came to site with full design context and no need to re-interpret another firm’s drawings. That continuity is what made the staged outage sequencing and the SEF check scheme work in practice.
Challenges and Approach
Three aspects of this project required more than standard engineering, and all three were solved in the design office before any outage was called.
The first was the staged SEF (Sensitive Earth Fault) check scheme. The existing and replacement transformers had different CT secondary ratings, which meant the existing SEF check scheme was not directly compatible with the new equipment during the intermediate stages of the commissioning sequence. Megavar identified this incompatibility during the design phase and developed a staged SEF check scheme that kept protection functional and compliant through every step of the staged commissioning, rather than finding the problem at a relay during an outage window with a clock ticking.
The second was the interlocking scheme for the 22 kV station service transformer, which needed to be supplied from either 22 kV Bus A via feeder B252 or 22 kV Bus B via feeder H252, but never both at once. Megavar designed and proposed a full interlocking arrangement to TasNetworks, which was then reviewed, modified and implemented in accordance with TasNetworks’ operational requirements. The final scheme satisfies the operational need, the safety requirement, and the relevant TasNetworks standards.
The third was a straightforward operational decision: the protection relay setting files were developed in the Megavar office from the approved setting reports, rather than being generated on site during each outage. The as-installed setting files were downloaded from the relays before the works began, and the new setting files were prepared, reviewed and verified against the scheme drawings ahead of mobilisation. That meant site outage time was spent verifying behaviour and energising equipment, not writing settings. It is the kind of sequencing decision that is easy to get wrong and quietly expensive when it goes wrong.
On site, the staged sequence was executed against the outage plan, with the two transformers, the station service transformer, the ring main unit and the 22 kV feeder protection all brought through integration, testing and commissioning in the planned windows. Protection relay commissioning stepped through the full installed suite: GE T60 transformer management, Siemens 7UT613 transformer differential, MicroTapp MT101 tap changer control, Areva P143 and P122 feeder and bus protection, and the RMS 2C138 element. The 22 kV cable work was proved with HV Diagnostics VLF testing alongside Omicron MPD 600 partial discharge measurement, and the SCADA integration was verified point-to-point through to the network control room.
Outcomes
Both T1 and T2 were replaced, integrated and commissioned successfully within the project timeline, along with a new 500 kVA 22/0.4 kV station service transformer and a new 22 kV ring main unit. The east coast distribution network now draws from two new 110/22 kV power transformers with upgraded protection and improved reliability.
- Both 110/22 kV 10 MVA power transformers T1 and T2 replaced, integrated and commissioned successfully within the agreed programme
- Staged SEF check scheme delivered working protection at every phase of the commissioning sequence, with no gap in functional protection at any point during the staged works
- 22 kV station service transformer interlocking scheme designed, reviewed with TasNetworks, and implemented without operational compromise
- Protection setting files pre-developed from approved setting reports, reducing site time spent on settings work and improving the quality of the outage execution
- 1 x 500 kVA 22/0.4 kV station service transformer and 1 x 22 kV ring main unit commissioned alongside the main transformers
- 22 kV cable circuits proved with VLF withstand and partial discharge testing, SCADA integration verified through to the TasNetworks control room
- TasNetworks indicated they would engage Megavar again on future work
Need High Voltage Testing or Equipment?
Talk to our engineers about your project requirements.
Get In TouchFrequently Asked Questions
What is involved in a 110/22 kV substation transformer replacement?
What is a Sensitive Earth Fault (SEF) check scheme and why does it matter?
What protection relays does Megavar commission?
How is 22 kV cable VLF and partial discharge testing performed?
Why was the St Marys substation upgrade important to TasNetworks?
Does Megavar deliver end-to-end substation design and commissioning?
Explore Our other services
Trusted by top enterprises for exceptional results
Explore the latest insights
We’re incredibly excited to share a big milestone in Megavar’s story—we’ve officially opened our new Newcastle branch, located at 22 Gavey Street, Mayfield,