St Marys Substation 110/22 kV Transformer Replacement

110 kV and 22 kV Voltage
2 x 110/22 kV 10 MVA power transformers plus associated 22 kV protection, SCADA, station service transformer and ring main unit Asset Type
St Marys Substation, east coast Tasmania Location
TasNetworks Client
April 2026 Completion
Client
TasNetworks
Location
St Marys Substation, east coast Tasmania, TAS
Voltage
110 kV and 22 kV
Asset Type
2 x 110/22 kV 10 MVA power transformers plus associated 22 kV protection, SCADA, station service transformer and ring main unit
Project Type
Asset replacement with end-to-end design, staged protection upgrade and full commissioning
Duration
Approximately 18 months end-to-end. Design scope November 2024 to IFC submission May 2025 (7 months). Testing and commissioning scope August 2025 to completion April 2026 (9 months).
Megavar Scope
Primary, secondary and SCADA design; staging and secondary isolation methodology; protection relay logic, settings and staged SEF check scheme; integration, testing and commissioning; closeout documentation
Technicians Performing High Voltage (HV) Substation Commissioning Inside a Control Room
Technician Inspecting Equipment During High Voltage (HV) Substation Commissioning

Overview

St Marys Substation sits on the east coast of Tasmania and supplies the distribution network that services Break O’Day and the surrounding east coast communities. The two 110/22 kV 10 MVA power transformers at St Marys, T1 and T2, had reached the point in their service lives where TasNetworks elected to replace them and upgrade the associated 22 kV protection at the same time.

TasNetworks engaged Megavar directly to deliver the project end to end. That scope covered the primary, secondary and SCADA design; the staging and secondary isolation methodology needed to remove the existing transformers safely; the protection setting work and a staged SEF check scheme to carry the site through each commissioning step; and the full testing and commissioning of the new equipment. The same Megavar team that produced the design package mobilised to site to commission it, which removes the design-to-commissioning interface risk that is normally carried between two contractors on a project of this size.

The work was executed on a live operational substation and sequenced around tightly controlled outage windows, with the 22 kV network supply to the east coast community needing to be maintained throughout. The project ran from design commencement in November 2024 through to commissioning completion in April 2026.

Scope of Work

  • Primary (high voltage) design for the replacement of T1 and T2, including plant layout, clearances and interface with the existing 110 kV and 22 kV switchyards
  • Secondary design covering protection, interlocking, DC supply, tripping, control and auxiliary schematics for the new transformers and associated 22 kV equipment
  • SCADA design covering points lists, alarm and event integration, remote control, and indication for the new transformers, station service transformer and ring main unit
  • Staging and secondary isolation methodology for the safe removal of the existing T1 and T2 while maintaining 22 kV supply to the east coast distribution network
  • Interlocking scheme design for the 22 kV station service transformer, which is supplied alternately from 22 kV Bus A via feeder B252 or 22 kV Bus B via feeder H252 (one bus at a time)
  • Staged Sensitive Earth Fault (SEF) check scheme design to accommodate the differing CT secondary ratings between the existing and new transformers during each phase of the staged commissioning
  • Preliminary Design Package and Issued for Construction (IFC) Design Package production, submitted May 2025
    Protection setting reports across the full relay suite, followed by protection setting files developed in the Megavar office from the approved setting reports
  • Inspection Test Plans and Commissioning Management Plans tailored to the staged outage sequence and TasNetworks acceptance requirements
  • Site staging execution, secondary isolation, integration and commissioning of the two new transformers and the associated 22 kV feeder and protection equipment
  • Protection relay commissioning across GE, Siemens, MicroTapp, Areva and RMS relay families
  • Site Acceptance Testing (SAT) of a new 22 kV station kiosk
    22 kV cable VLF (Very Low Frequency) withstand testing and partial discharge measurement
  • SCADA testing including point-to-point verification, alarm and event propagation to the network control room, and remote control proving
  • Commissioning of a 500 kVA 22/0.4 kV station service transformer and a 22 kV ring main unit
  • As-built drawings, commissioning records, and site handover package

Equipment
Commissioned

  • 2 x 110/22 kV 10 MVA power transformers (T1 and T2)
  • 2 x GE T60 transformer management relays
  • 2 x Siemens 7UT613 transformer differential relays
  • 2 x MicroTapp MT101 tap changer controllers
  • 2 x Areva P143 protection relays (110 kV side)
  • 5 x Areva P143 protection relays (22 kV side)
  • 3 x Areva P122 protection relays (22 kV side)
  • 1 x RMS 2C138 protection relay (22 kV side)
  • 1 x 22 kV station kiosk (Site Acceptance Testing)
  • 1 x 500 kVA 22/0.4 kV station service transformer
  • 1 x 22 kV ring main unit
  • 22 kV cable circuits (VLF and partial discharge proved)
  • SCADA integration, communications and control room alarms

Megavar Test Equipment Deployed

  • Omicron CMC 500 protection relay test set
  • Omicron CMC 356 protection relay test set
  • Omicron CPC 100 primary injection test set
  • Omicron TESTRANO 600 transformer diagnostic test set
  • Omicron MPD 600 partial discharge measurement system
  • HV Diagnostics HVA60 VLF test set (22 kV cable testing)
  • Phoenix 6CP50 50 kV HiPot test set
  • Megger MIT 515 (5 kV insulation resistance tester)
  • Megger DLRO 600 micro-ohmmeter

Team: Megavar delivered the project with a multi-discipline team across two phases. The design phase was led by a senior design engineer supported by primary and secondary design engineers and drafters. The testing and commissioning phase was led by dedicated T&C engineers supported by field testers. Overall project management sat with a dedicated Megavar project manager through the full duration.


Handing the project through from Megavar’s design team to Megavar’s T&C team meant the commissioning engineers came to site with full design context and no need to re-interpret another firm’s drawings. That continuity is what made the staged outage sequencing and the SEF check scheme work in practice.

New ABB UniGear ZS1 11 kV switchgear in service at Chapel Street Substation, commissioned by Megavar

Challenges and Approach

Three aspects of this project required more than standard engineering, and all three were solved in the design office before any outage was called.

The first was the staged SEF (Sensitive Earth Fault) check scheme. The existing and replacement transformers had different CT secondary ratings, which meant the existing SEF check scheme was not directly compatible with the new equipment during the intermediate stages of the commissioning sequence. Megavar identified this incompatibility during the design phase and developed a staged SEF check scheme that kept protection functional and compliant through every step of the staged commissioning, rather than finding the problem at a relay during an outage window with a clock ticking.

 

The second was the interlocking scheme for the 22 kV station service transformer, which needed to be supplied from either 22 kV Bus A via feeder B252 or 22 kV Bus B via feeder H252, but never both at once. Megavar designed and proposed a full interlocking arrangement to TasNetworks, which was then reviewed, modified and implemented in accordance with TasNetworks’ operational requirements. The final scheme satisfies the operational need, the safety requirement, and the relevant TasNetworks standards.

 

The third was a straightforward operational decision: the protection relay setting files were developed in the Megavar office from the approved setting reports, rather than being generated on site during each outage. The as-installed setting files were downloaded from the relays before the works began, and the new setting files were prepared, reviewed and verified against the scheme drawings ahead of mobilisation. That meant site outage time was spent verifying behaviour and energising equipment, not writing settings. It is the kind of sequencing decision that is easy to get wrong and quietly expensive when it goes wrong.

 

On site, the staged sequence was executed against the outage plan, with the two transformers, the station service transformer, the ring main unit and the 22 kV feeder protection all brought through integration, testing and commissioning in the planned windows. Protection relay commissioning stepped through the full installed suite: GE T60 transformer management, Siemens 7UT613 transformer differential, MicroTapp MT101 tap changer control, Areva P143 and P122 feeder and bus protection, and the RMS 2C138 element. The 22 kV cable work was proved with HV Diagnostics VLF testing alongside Omicron MPD 600 partial discharge measurement, and the SCADA integration was verified point-to-point through to the network control room.

Outcomes

Both T1 and T2 were replaced, integrated and commissioned successfully within the project timeline, along with a new 500 kVA 22/0.4 kV station service transformer and a new 22 kV ring main unit. The east coast distribution network now draws from two new 110/22 kV power transformers with upgraded protection and improved reliability.

 

  • Both 110/22 kV 10 MVA power transformers T1 and T2 replaced, integrated and commissioned successfully within the agreed programme
  • Staged SEF check scheme delivered working protection at every phase of the commissioning sequence, with no gap in functional protection at any point during the staged works
  • 22 kV station service transformer interlocking scheme designed, reviewed with TasNetworks, and implemented without operational compromise
  • Protection setting files pre-developed from approved setting reports, reducing site time spent on settings work and improving the quality of the outage execution
  • 1 x 500 kVA 22/0.4 kV station service transformer and 1 x 22 kV ring main unit commissioned alongside the main transformers
  • 22 kV cable circuits proved with VLF withstand and partial discharge testing, SCADA integration verified through to the TasNetworks control room
  • TasNetworks indicated they would engage Megavar again on future work
Megavar engineer FAT testing a Siemens 7SJ82 feeder protection relay for Chapel Street 11 kV switchgear

Need High Voltage Testing or Equipment?

Talk to our engineers about your project requirements.

Get In Touch

Frequently Asked Questions

What is involved in a 110/22 kV substation transformer replacement?
A 110/22 kV substation transformer replacement involves the primary design for the new transformers and their interface with the existing switchyard, the secondary and SCADA design to integrate the new protection and control equipment, a staged outage methodology to remove the existing transformers without losing supply to the connected network, protection setting work, and the site integration, testing and commissioning. On the St Marys project, Megavar delivered this end to end for TasNetworks across two 110/22 kV 10 MVA transformers.
A Sensitive Earth Fault check scheme is a protection arrangement that detects low-magnitude earth fault currents by comparing measurements from different points in the system before issuing a trip. The scheme is sensitive to the CT secondary ratings at each measurement point, which means a check scheme designed for one set of CTs does not automatically transfer to equipment with different CT ratings. On the St Marys project, Megavar identified that the existing and new transformers had different CT secondary ratings and designed a staged SEF check scheme so that the check protection remained functional through each phase of the staged commissioning.
Megavar commissions protection relays from all major vendors used on the Australian network, including GE (T60, D60, L90, Multilin platforms), Siemens (SIPROTEC 7SJ, 7SD, 7UT, and legacy 7UT613), MicroTapp tap changer controllers, Areva / AlstomSchneider MiCOM (P122, P143, P14x, P84x), SEL (351, 411, 421, 451, 751), RMS (including the 2C138), and legacy electromechanical relays. The St Marys project required commissioning across GE, Siemens, MicroTapp, Areva and RMS platforms in a single scope.
VLF (Very Low Frequency) testing applies an AC test voltage at a frequency in the 0.01 Hz to 0.1 Hz range, which allows the cable insulation to be stressed at a meaningful voltage without the large test equipment that would be needed for 50 Hz testing on the same circuit. Partial discharge (PD) measurement is run in parallel with the VLF test to detect and locate any discharge activity in the cable or its terminations. Megavar used an HV Diagnostics HVA60 VLF test set and an Omicron MPD 600 partial discharge measurement system on the St Marys 22 kV cable work.
St Marys Substation is the 110/22 kV supply point for the Break O’Day and east coast Tasmania distribution network. The two original 10 MVA transformers were approaching the end of their service lives, and replacing them along with the associated 22 kV protection allowed TasNetworks to improve reliability and resilience for an asset that supplies a regional community with long travel times and limited redundancy.
Yes. Megavar delivers primary, secondary and SCADA design, protection engineering, and site testing and commissioning from the same in-house team. On the St Marys project, the Megavar design team produced the Issued for Construction package and the Megavar T&C team mobilised from that same package, which removes the design-to-commissioning interface risk that normally sits between two separate contractors on a project of this size.

Explore Our other services

HV testing and commissioning by Megavar's own engineers. Substations, transformers, cables, switchgear. 200+ instrument fleet, four offices nationwide.

Substation maintenance services: preventive, corrective, and condition-based maintenance for HV transformers, switchgear, protection, and SCADA across Australia. Omicron test equipment.

Solar farm HV maintenance and testing: transformer diagnostics, switchgear testing, protection relay verification, thermography, and DGA monitoring for solar farms across Australia.

Trusted by top enterprises for exceptional results

AusNet logo - Megavar client
ABB logo - Megavar client
ElectraNet logo - Megavar client
Fluence logo - Megavar client
RJE Global logo - Megavar client
NYRStar logo - Megavar client
Schneider Electric logo - Megavar client
Acciona logo - Megavar client
RBD Electrical logo - Megavar client
Ventia logo - Megavar client
Grange logo - Megavar client
Alcoa logo - Megavar client
Zinfra logo - Megavar client
Bison Energy Company logo - Megavar client
Hydro Tasmania logo - Megavar client
TasNetworks logo - Megavar client
Vestas logo - Megavar client
Goldwind logo - Megavar client
Downer logo - Megavar client
ENERVEN logo - Megavar client
Genus logo - Megavar client

Explore the latest insights